Mifflin Drive – Gas Emergency Impact Area

The Department of Public Works (DPW), with the help of the Town’s contractor, is looking to upgrade Mifflin Drive’s road surface and add new sidewalk with vertical granite curb extending from Massachusetts Avenue to Middlesex Road. 

The DPW will be conducting a meeting on Tuesday, April 16th to discuss the redesign with a meeting point at the following time and location:

·         5:00 pm – corner of Mifflin Drive and Middlesex Street

Department engineers will meet individually with abutters along the way to discuss any specific questions and concerns for locations throughout the neighborhood. If you are unable to attend this meeting or have other concerns, please contact the DPW to schedule an individual appointment or phone call with you.

Complete Streets Improvement Project

As part of the Complete Streets Improvement Project, the town’s contractor, Tasco Construction will begin work at the Sutton Street at High Street intersection. A street layout is expected to begin Tuesday, April 16th with construction expected to begin shortly after. A representative of the town engineering department will be on site to help answer any questions. Raised castings and traffic delays should be anticipated for anyone traveling in the area.

Annual Road & Sidewalk Restoration Program

As part of the Annual Road & Sidewalk Restoration Program, work will begin on High Street from Water Street to Sutton Street in the coming weeks with additional roads to follow:

The Town’s contractor, D&R, will begin sidewalk layouts and construction the week of April 15th with sloped granite curbing and new asphalt sidewalk to be installed from Prescott Street to Sutton Street. Milling of the roadway is expected shortly after, followed by casting adjustments and then finish paving after that (weather permitting). Raised castings and traffic delays should be anticipated for anyone traveling in the area.

Gas Restoration Contract Areas 3-4-5 Construction Update

Starting today, April 1, 2024, the Town’s contractor PJ Albert will be starting back up on the gas restoration activities in the Contract 3-4-5 areas.  Work will begin on replacing the curbing along Middlesex Street and Edmands Road with new sloped granite curbing and then preparing the sidewalk and road surfaces for restoration along the following roadways:  Edmands Road, Morris Street, Middlesex Street, 2nd Street, 3rd Street, Milton Street, Richardson Avenue, and Pilgrim Street.  Delays should be expected if traveling in these areas.

 

Thank you.


https://mvgas.northandoverma.gov/

4.1.24 gas restoration areas 3-4-5.jpg

Reminder: Roadway Construction Notification: Columbia Gas Impact Contract 3 Area, Starting Monday, October 16, 2023

As part of the Columbia Gas Impact Area restoration program, the town's contractor, PJ Albert, will be starting paving work on Monday, October 16th in the Contract 3 area. The anticipated schedule for paving is as follows:

 

· Day 1 (Monday): Norman Road, Cabot Street, Saltonstall Road, Chapin Road, and Buckingham Road (Middlesex to Herrick)

· Day 2 (Tuesday): Young Road, Herrick Road and Waverly Road & Mass Ave Intersection

· Day 3 (Wednesday): Buckingham Road, Edmands Road, and Silsbee Road

 

Work is anticipated to begin at 7:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas.


North Andover Road Construction and Road Closures Map

contract 3.jpg

Roadway Construction Notification: Essex Street, Great Pond Road, and Chestnut Street, Week of October 16, 2023

As part of the Town’s annual road and sidewalk restoration program, the town's contractor, D&R Paving, will be starting paving work on Monday, October 16th. The schedule for paving is as follows:

 

· Day 1 (Monday): Essex Street @ Town Border to approx. 808 Great Pond Road

· Day 2 (Tuesday): Approx. 808 Great Pond Road to Country Club Circle

· Day 3 (Wednesday): Country Club Circle and the remainder of Great Pond Road

· Day 4 (Friday): Chestnut Street from Blueberry Hill Lane to Woodlea Road

 

Work is anticipated to begin at 9:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas.  Attached are the proposed detour maps if traveling in this area.

North Andover Road Construction and Road Closures Map

contruction essex, great pond, chestnut.jpg


Roadway Construction Notification: Columbia Gas Impact Contract 3 Area, Starting Monday, October 16, 2023

As part of the Columbia Gas Impact Area restoration program, the town's contractor, PJ Albert, will be starting paving work on Monday, October 16th in the Contract 3 area. The anticipated schedule for paving is as follows:

 

· Day 1 (Monday): Norman Road, Cabot Street, Saltonstall Road, Chapin Road, and Buckingham Road (Middlesex to Herrick)

· Day 2 (Tuesday): Young Road, Herrick Road and Waverly Road & Mass Ave Intersection

· Day 3 (Wednesday): Buckingham Road, Edmands Road, and Silsbee Road

 

Work is anticipated to begin at 7:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas.


North Andover Road Construction and Road Closures Map

contract 3.jpg

Roadway Construction Notification: Essex Street, Great Pond Road, and Chestnut Street Roadway Construction – Starting Next Wednesday October 4, 2023

The Town's contractor – D&R Paving will begin roadway construction including milling, castings adjustment, and repaving next Wednesday October 4, 2023.  Milling will begin on Essex Street starting at the Boxford Town Line and then continuing on Great Pond Road from Essex Street to Marbleridge Road and then moving to Chestnut Street from Blueberry Hill Lane to Wood Lea.  Milling is expected to take 3-4 days to complete followed by one week for casting adjustments and then finish paving after that (weather permitting). The contractor has been asked to keep at least 1 lane of traffic open during construction, but at times, due to roadway curvature or temperature concerns with finish paving, sections of road may need to be closed in both directions for short periods of time.  The contractor is going to work with the NAPD to determine if the need for any closures are required.  Delays should be anticipated for anyone traveling in these areas.
roadwork october 4.jpg

Upcoming Road Construction

Starting tomorrow, Wednesday, September 13, 2023, the Town's contractor, PJ Albert, will be starting the reconstruction of sections of the following roads:  Norman Road, Buckingham Road, Herrick Road, Chapin Road, Silsbee Road, Edmands Road, Young Road and Saltonstall Road.  Pavement milling will be completed over the next few days and raised castings should be expected. Delays should be anticipated if travelling in these areas.

road construction (3).png



Stevens Street Road Closure Notification – Wednesday November 16, 2022

Tomorrow, Wednesday, November 16, 2022, the Town’s contractor, Veteran Diving, will be diving to complete the cleaning out of the two existing culverts that connect Stevens Pond and Mill Pond on Stevens Street.  During this time the bridge area on Stevens Street between Pleasant Street and Harkaway Road will be closed and traffic will be detoured.  Delays should be anticipated if travelling in this area. 

road work stevens st.jpg