· Day 1 (Monday): Essex Street @ Town Border to approx. 808 Great Pond Road
· Day 2 (Tuesday): Approx. 808 Great Pond Road to Country Club Circle
· Day 3 (Wednesday): Country Club Circle and the remainder of Great Pond Road
· Day 4 (Friday): Chestnut Street from Blueberry Hill Lane to Woodlea Road
Work is anticipated to begin at 9:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas. Attached are the proposed detour maps if traveling in this area.
North Andover Road Construction and Road Closures Map

Reminder: Roadway Construction Notification: Columbia Gas Impact Contract 3 Area, Starting Monday, October 16, 2023
As part of the Columbia Gas Impact Area restoration program, the town's contractor, PJ Albert, will be starting paving work on Monday, October 16th in the Contract 3 area. The anticipated schedule for paving is as follows:
· Day 1 (Monday): Norman Road, Cabot Street, Saltonstall Road, Chapin Road, and Buckingham Road (Middlesex to Herrick)
· Day 2 (Tuesday): Young Road, Herrick Road and Waverly Road & Mass Ave Intersection
· Day 3 (Wednesday): Buckingham Road, Edmands Road, and Silsbee Road
Work is anticipated to begin at 7:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas.
North Andover Road Construction and Road Closures Map