As part of the Town’s annual road and sidewalk restoration program, the town's contractor, D&R Paving, will be starting paving work on Monday, October 16th. The schedule for paving is as follows:
· Day 1 (Monday): Essex Street @ Town Border to approx. 808 Great Pond Road
· Day 2 (Tuesday): Approx. 808 Great Pond Road to Country Club Circle
· Day 3 (Wednesday): Country Club Circle and the remainder of Great Pond Road
· Day 4 (Friday): Chestnut Street from Blueberry Hill Lane to Woodlea Road
Work is anticipated to begin at 9:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas. Attached are the proposed detour maps if traveling in this area.
North Andover Road Construction and Road Closures Map



