Roadway Construction Notification: Columbia Gas Impact Contract 3 Area, Starting Monday, October 16, 2023

As part of the Columbia Gas Impact Area restoration program, the town's contractor, PJ Albert, will be starting paving work on Monday, October 16th in the Contract 3 area. The anticipated schedule for paving is as follows:

 

· Day 1 (Monday): Norman Road, Cabot Street, Saltonstall Road, Chapin Road, and Buckingham Road (Middlesex to Herrick)

· Day 2 (Tuesday): Young Road, Herrick Road and Waverly Road & Mass Ave Intersection

· Day 3 (Wednesday): Buckingham Road, Edmands Road, and Silsbee Road

 

Work is anticipated to begin at 7:00 am, weather permitting. Delays and road closures should be anticipated if travelling in these areas.


North Andover Road Construction and Road Closures Map