As part of the annual roads repaving program, the following work is proposed to start tomorrow, May 30, 2024:
Thursday, May 30th: Milling @:
· High St from Chadwick St to Water St
· Johnson St from Salem St to Johnson Cir
Friday, May 31st: Milling @:
· Heath Rd from Milk St to Sutton Hill Rd
· Heath Cir from Heath Rd to Cul-De-Sac
· Rosemont Dr from Ridge Way to Cul-de-sac
Starting Monday, June 3rd
· Casting adjustments on all streets identified above.
With this construction work, raised castings and traffic delays should be expected. Paving of the roadways will follow and is anticipated to start June 6, 2024, weather permitting. If you have any questions, a representative from the town will be on site during construction.
We appreciate your understanding during construction. Residents should expect delays if travelling in these areas. For any questions, please do not hesitate to reach out to the engineering department.